Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Direct Field Costs$71.7M
Module Shop Fabrication$16.3M
Site Installation$22.9M
Major Equipment$31.6M
Indirect Field Costs$6.7M
Engineering$2.2M
Project Management$4.4M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$78.4M

CLECO / Brame Energy Center Madison 3 Unit

CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
MW
CO₂ concentration
14.1%vol%
Direct Field Costs$667.2M
Absorber$37.0M
Indirect Field Costs$509.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$120.7M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.30B

Finnish Market Pulp Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
Direct Field Costs$325.6M
Lime Kiln: booster fan and ductwork$0.2M
Multi-fuel boiler: booster fan and ductwork$0.3M
Steam turbine island modifications$10.0M
Waste water treatment$4.5M
Common flue gas stack$1.1M
Direct Contact Cooler$5.2M
Amine absorber section$36.8M
Amine circulation system$3.5M
Stripper section$80.3M
CO2 Compression and dehydration$9.8M
Auxiliaries$1.2M
Other direct material cost$26.5M
Construction$97.1M
EPC and other costs$47.4M
Recovery Boiler: booster fan and ductwork$0.6M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$32.6M
Contingency$32.6M
Interest During Construction$52.9M
Report did not provide a further cost breakdown.
Owners Cost$36.8M
Report did not provide a further cost breakdown.
Total Capex$447.8M