Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Direct Field Costs$575.3M
Solvent Reclaiming
Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead
EPC engineering and detailed design
Contingency & Escalation$145.5M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$23.6M
Owner's cost
Total Capex$849.3M

CEMEX / Balcones Cement Plant

Cementpre-FEED· Membrane Technology and Research (MTR)· 2022-06-03Project page ↗Cost report ↗
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Direct Field Costs$262.6M
Pre-commisioning and Startup
Indirect Field Costs$123.7M
Project Indirects
Construction Indirect
Contingency & Escalation$123.9M
Contingency
Escalation
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$510.2M

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Direct Field Costs$89.1M
CO2 Compression Equipment
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$89.1M