Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Direct Field Costs$575.3M
Module Shop Fabrication$16.3M
Site Installation$23.9M
Absorber, cooling system, compression, vessels, pumps$230.3M
Piping materials, ductwork, racks$59.3M
Civil materials, concrete, site materials$49.7M
Structural steel materials$19.7M
Electrical materials and equipment$39.6M
Instruments and automation hardware$8.9M
Insulation materials$1.0M
Paint and coatings$0.1M
Freight, heavy lift, hauling$18.0M
All field installation labor$149.1M
Major Equipment$31.6M
Indirect Field Costs$104.9M
Construction management, supervision, temporary facilities, overhead$54.3M
EPC engineering and detailed design$50.6M
Contingency & Escalation$145.5M
Contingency$104.0M
Escalation$41.5M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$23.6M
Owner's cost$23.6M
Total Capex$849.3M

Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Lime Kiln only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
Direct Field Costs$52.8M
Instrumentaiton and Control$7.8M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$5.3M
Contingency$5.3M
Interest During Construction$8.6M
Report did not provide a further cost breakdown.
Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.5M

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Direct Field Costs$2.17B
Auxiliary power and fans$94.1M
Absorber$288.0M
Common facilities$327.5M
Carbon Capture Plant$1.45B
Switchyard$6.2M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.17B