Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Direct Field Costs$1.10B
CO2 Technology
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$192.4M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.29B

Calpine / Deer Park Energy Center

Natural GasFEED· Calpine· 2024-05-30Project page ↗Cost report ↗
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Direct Field Costs$1.32B
Civil structural work
Indirect Field Costs$754.3M
Indirect Field Costs
Contingency & Escalation$303.0M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.38B

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Direct Field Costs$2.17B
Combustion Turbine & Accessories
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.17B