Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Direct Field Costs$2.17B
Combustion Turbine & Accessories
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.17B

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Modularization
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs
Total Capex$411.5M

Rayburn Energy Station / Sherman Power Plant

Natural GasFEED· Bechtel· 2022-03-01Project page ↗Cost report ↗
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Direct Field Costs$385.9M
Distribution control system (DCS), communication, main power supply, all distribution system, auxiliary system
Indirect Field Costs$59.1M
Construction preliminaries
Engineering
Mechanical completion, commissioning and testing
Training
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction$27.0M
Report did not provide a further cost breakdown.
Owners Cost$5.0M
Report did not provide a further cost breakdown.
Total Capex$477.0M