Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Gerald Gentleman Station
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
—
▸Direct Field Costs$2.17B
Auxiliary power and fans$94.1M
Absorber$288.0M
Common facilities$327.5M
Carbon Capture Plant$1.45B
Switchyard$6.2M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation—
Report did not provide a further cost breakdown.
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost—
Report did not provide a further cost breakdown.
Total Capex$2.17B
CRC / Elk Hills Power Plant
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
▸Direct Field Costs$444.7M
Concrete$51.1M
Structural Steel$19.1M
Capture Plant Equipment$104.7M
Utilities Equipment$58.5M
CO2 Compression Equipment$20.1M
Piping$69.4M
Electrical and Control Systems$47.2M
Scaffolding, Painting, Insulation$22.1M
Modularization$1.1M
Procurement, Taxes & Duties$26.0M
Pre-commisioning and Startup$5.8M
Earthwork & Civil$19.4M
▸Indirect Field Costs$206.3M
Indirect Field Costs$91.9M
Home Office$47.8M
EPC Fees$66.5M
▸Contingency & Escalation$96.0M
Escalation$39.0M
Contingency$57.0M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M
Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Lime Kiln only
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
▸Direct Field Costs$52.8M
Steam turbine island modifications$6.4M
Waste water treatment$4.0M
Direct Contact Cooler$0.7M
Amine absorber section$5.0M
Amine circulation system$0.5M
Stripper section$11.0M
CO2 Compression and dehydration$1.3M
Auxiliaries$0.2M
Other direct material cost$3.6M
Construction$13.3M
EPC and other costs$5.6M
Lime Kiln: booster fan and ductwork$0.2M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$5.3M
Contingency$5.3M
▸Interest During Construction$8.6M
Report did not provide a further cost breakdown.
▸Owners Cost$5.9M
Report did not provide a further cost breakdown.
Total Capex$72.5M