Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection47 reports
Comparing 3 reports — tab selection applies to every column.

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Direct Field Costs$2.17B
Auxiliary power and fans$94.1M
Absorber$288.0M
Common facilities$327.5M
Carbon Capture Plant$1.45B
Switchyard$6.2M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.17B

Quest CCS — Scotford Upgrader

Bitumen upgrading — hydrogen productionFEED· Shell· 2021-01-01Project page ↗Cost report ↗
CO₂ captured
1,200,000t/yr
Capture efficiency
80.0%
Utilization
99.0%
Parasitic load
MW
CO₂ concentration
15.0%vol%
Direct Field Costs$483.8M
Construction & Commissioning$372.8M
Capture Facility Components & Procurement$110.9M
Indirect Field Costs$183.0M
FEED and Detailed Engineering$183.0M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$666.7M

Finnish Market Pulp Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
Direct Field Costs$325.6M
Lime Kiln: booster fan and ductwork$0.2M
Multi-fuel boiler: booster fan and ductwork$0.3M
Steam turbine island modifications$10.0M
Waste water treatment$4.5M
Common flue gas stack$1.1M
Direct Contact Cooler$5.2M
Amine absorber section$36.8M
Amine circulation system$3.5M
Stripper section$80.3M
CO2 Compression and dehydration$9.8M
Auxiliaries$1.2M
Other direct material cost$26.5M
Construction$97.1M
EPC and other costs$47.4M
Recovery Boiler: booster fan and ductwork$0.6M
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation$32.6M
Contingency$32.6M
Interest During Construction$52.9M
Report did not provide a further cost breakdown.
Owners Cost$36.8M
Report did not provide a further cost breakdown.
Total Capex$447.8M