Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Direct Field Costs$1.34B
Cooling Water System
Indirect Field Costs$61.5M
Project Management
Limited Notice to Proceed
Services
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$470.0M
Owner's Cost Contingency
EPC Contingency
Escalation
Regional Adjustment for Labor
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$71.2M
Spare Parts
License fee
Insurance
Startup
Miscellaneous
Total Capex$1.95B

Gerald Gentleman Station

CoalFEED· ION Clean Energy· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
4,316,020t/yr
Capture efficiency
89.8%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
Direct Field Costs$2.17B
Combustion Turbine & Accessories
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$2.17B

Prairie State Generating

CoalFEED· University of Illinois· 2022-09-03Project page ↗Cost report ↗
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
11.4%vol%
Direct Field Costs$1.89B
CO2 Capture System
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B