Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Daniel

Natural GasFEED· Southern Company· 2022-11-30Project page ↗Cost report ↗
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
79MW
CO₂ concentration
Direct Field Costs$515.2M
Instrumentation & Control
Indirect Field Costs$56.6M
Project Management
Engineering – Including Construction and Startup Support
Contingency & Escalation$126.3M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$54.1M
Front End Planning
Startup
Other's owners cost
Total Capex$752.2M

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Direct Field Costs$384.1M
Earthwork & Civil
Indirect Field Costs$209.7M
Indirect Field Costs
Contractor’s Profit
Engineering
Miscellaneous Project Expenses (Insurance, taxes, bonds & permits)
Contingency & Escalation$104.6M
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$28.0M
Report did not provide a further cost breakdown.
Total Capex$726.4M

CRC / Elk Hills Power Plant

Natural GasFEED· Electric Power Research Institute (EPRI)· 2020-09-01Project page ↗Cost report ↗
CO₂ captured
1,460,000t/yr
Capture efficiency
90.0%
Utilization
95.0%
Parasitic load
35MW
CO₂ concentration
4.3%mol%
Direct Field Costs$444.7M
Solvent regeneration
Indirect Field Costs$206.3M
Indirect Field Costs
Home Office
EPC Fees
Contingency & Escalation$96.0M
Escalation
Contingency
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$47.8M
Report did not provide a further cost breakdown.
Total Capex$794.8M