Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Daniel

Natural GasFEED· Southern Company· 2022-11-30Project page ↗Cost report ↗
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
79MW
CO₂ concentration
Direct Field Costs$515.2M
Construction – Including Labor, Materials, and Contracted Equipment$497.1M
Engineering-Procured Materials$18.1M
Indirect Field Costs$56.6M
Project Management$8.7M
Engineering – Including Construction and Startup Support$47.9M
Contingency & Escalation$126.3M
Contingency$126.3M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$54.1M
Front End Planning$4.5M
Startup$31.8M
Other's owners cost$17.8M
Total Capex$752.2M

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Direct Field Costs$1.65B
Coal & Sorbent Prep & Feed Equipment$13.5M
Feedwater & Misc. Balance of Plant Systems Equipment$50.1M
Pulverized coal-fired boiler Equipment$297.9M
Flue Gas Cleanup Equipment$81.3M
CO2 Capture System Equipment$154.4M
CO2 Compression and Purification Equipment$80.5M
HRSG, Ducting & Stack Equipment$8.7M
Steam Turbine Generator Equipment$131.5M
Cooling Water System Equipment$34.9M
Ash/Spent Sorbent Handling System Equipment$5.0M
Accessory Electric Plant Equipment$34.0M
Instrumentation & Control Equipment$12.6M
Improvements to Site Equipment$2.6M
Materials$66.3M
Labor$626.7M
Coal & Sorbent Handling Equipment$48.5M
Indirect Field Costs$187.0M
Engineering$187.0M
Contingency & Escalation$418.3M
Project Contingency$417.5M
Process Contingency$0.8M
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$507.6M
Financing Cost$60.9M
Pre-production Cost$66.8M
Inventory Capital$37.9M
Other's owners cost$342.0M
Total Capex$3.19B

CLECO / Brame Energy Center Madison 3 Unit

CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
MW
CO₂ concentration
14.1%vol%
Direct Field Costs$667.2M
Absorber$37.0M
Indirect Field Costs$509.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$120.7M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.30B