Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Southern Company / Plant Daniel
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
—
▸Direct Field Costs$515.2M
Construction – Including Labor, Materials, and Contracted Equipment$497.1M
Engineering-Procured Materials$18.1M
▸Indirect Field Costs$56.6M
Project Management$8.7M
Engineering – Including Construction and Startup Support$47.9M
▸Contingency & Escalation$126.3M
Contingency$126.3M
▸Interest During Construction—
Report did not provide a further cost breakdown.
▸Owners Cost$54.1M
Front End Planning$4.5M
Startup$31.8M
Other's owners cost$17.8M
Total Capex$752.2M
Finnish Integrated Pulp and Board Mill / Capture of CO2 in both Kraft & Multi-boilers
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,749,600t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
28.5MW
CO₂ concentration
15.0%mol%
▸Direct Field Costs$366.5M
Feedwater & Misc. Balance of Plant Equipment & Systems$180.5M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$36.7M
Contingency$36.7M
▸Interest During Construction$59.7M
Report did not provide a further cost breakdown.
▸Owners Cost$43.2M
Report did not provide a further cost breakdown.
Total Capex$506.0M
Finnish Market Pulp Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
▸Direct Field Costs$325.6M
Lime Kiln: booster fan and ductwork$0.2M
Multi-fuel boiler: booster fan and ductwork$0.3M
Steam turbine island modifications$10.0M
Waste water treatment$4.5M
Common flue gas stack$1.1M
Direct Contact Cooler$5.2M
Amine absorber section$36.8M
Amine circulation system$3.5M
Stripper section$80.3M
CO2 Compression and dehydration$9.8M
Auxiliaries$1.2M
Other direct material cost$26.5M
Construction$97.1M
EPC and other costs$47.4M
Recovery Boiler: booster fan and ductwork$0.6M
▸Indirect Field Costs—
Report did not provide a further cost breakdown.
▸Contingency & Escalation$32.6M
Contingency$32.6M
▸Interest During Construction$52.9M
Report did not provide a further cost breakdown.
▸Owners Cost$36.8M
Report did not provide a further cost breakdown.
Total Capex$447.8M