Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Prairie State Generating

CoalFEED· University of Illinois· 2022-09-03Project page ↗Cost report ↗
CO₂ captured
7,676,700t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
11.4%vol%
Direct Field Costs$1.89B
CO2 Capture System
Indirect Field Costs
Report did not provide a further cost breakdown.
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$228.5M
Report did not provide a further cost breakdown.
Total Capex$2.12B

CLECO / Brame Energy Center Madison 3 Unit

CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
MW
CO₂ concentration
14.1%vol%
Direct Field Costs$667.2M
Absorber
Indirect Field Costs$509.3M
Report did not provide a further cost breakdown.
Contingency & Escalation$120.7M
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$1.30B

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Direct Field Costs$292.8M
Modularization
Indirect Field Costs$91.1M
BEC + Engineering, Construction, Management, Home Office & Contractor Premiums, Allowances & Freight, and Process & Project Contingencies
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost$27.6M
Pre-Production Costs, Inventory Capital, Financing Costs and Other Owner Costs
Total Capex$411.5M