Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

47 reports

Quest CCS — Scotford Upgrader

Bitumen upgrading — hydrogen productionFEED· Shell· 2021-01-01Project page ↗Cost report ↗
CO₂ captured
1,200,000t/yr
Capture efficiency
80.0%
Utilization
99.0%
Parasitic load
MW
CO₂ concentration
15.0%vol%
Direct Field Costs$483.8M
Construction & Commissioning$372.8M
Capture Facility Components & Procurement$110.9M
Indirect Field Costs$183.0M
FEED and Detailed Engineering$183.0M
Contingency & Escalation
Report did not provide a further cost breakdown.
Interest During Construction
Report did not provide a further cost breakdown.
Owners Cost
Report did not provide a further cost breakdown.
Total Capex$666.7M