In March 2010, the Scottish CCS (Carbon Capture & Storage) Consortium began an extensive Front End, Engineering and Design (FEED) study to assess what exactly would be required from an engineering, commercial and regulatory, perspective in order to progress the CCS demonstration project at Longannet Power station in Scotland (Goldeneye) through to construction. The study has yielded invaluable knowledge in areas such as cost, design, end-to-end CCS chain operation, health and safety, environment, consent and permitting, risk management, and lessons learnt.
CO₂ capture
2,000,000 t/yr
Status
Cancelled
Sector
Natural Gas Power
Year announced
Mar-2010
Overview
Full Project Overview
All key information and technical data related to this project
Overview
Company:
Project name:
Longannet ScottishPower Carbon Capture and Storage Project
Project categories:
capture
County:
Fife
State:
Scotland
Country:
United Kingdom
Region:
Europe
Sector:
Natural gas power
Sequestration project:
EPC company:
Aker Clean Carbon
Transport partner:
National Grid
Storage partner:
Shell
Capacity (Mt/year):
2,000,000
Status:
Cancelled
Technology licensor:
Aker Clean Carbon
Date announced:
Mar-2010