classVIGoose Lake
Company Logo

Gulf Coast Sequestration

Goose Lake

The Goose Lake CCS Project, led by Gulf Coast Sequestration, LLC (GCS), is located in Calcasieu Parish, Louisiana, north of the Gulf Intracoastal Waterway. The project will begin with two injection wells—Goose Lake CCS Well No. 001 (GL CCS 1) and Goose Lake CCS Well No. 002 (GL CCS 2)—targeting the upper Frio Formation for permanent CO₂ storage. GCS has partnered with local landowners to secure long-term site access and will source CO₂ primarily from regional emitters in the Lake Charles, LA, and Beaumont, TX industrial corridors, where over 36 million metric tons (MMT) of CO₂ were emitted in 2023. The captured CO₂ stream is expected to come from natural gas processing, LNG facilities, and blue hydrogen production, with high-purity specifications aligned with existing Gulf Coast pipeline networks. The facility is designed for a 15-year injection period, sequestering about 2.0 MMT of CO₂ annually for a total of 30.1 MMT. GL CCS 1 is expected to store ~7.4 MMT, while GL CCS 2 will store ~22.7 MMT over the project life. The overall project timeline spans 94 years, including 4 years of permitting and construction, 15 years of active injection, and a 70-year post-injection site care (PISC) phase. Extensive site characterization, geomechanical studies, seismic risk assessments, and monitoring plans have been completed to demonstrate long-term storage security and regulatory compliance.

State

Louisiana

Country

United States of America

Region

us

Project name

Goose Lake

Overview

Full Project Overview

All key information and technical data related to this project

Overview

Project name:
Goose Lake
Project categories:
class_vi
County:
Calcasieu
State:
Louisiana
Country:
United States of America
Region:
United States
Applicant name:
Gulf Coast Sequestration, LLC
Status:
Pending
Well applications:
2
Injection rate (Mt/year):
2,000,000
Total storage capacity (Mt):
30,000,000
Announcement date:
2020-10-18
News

Related News

Explore recent news and developments connected to this project.

Date
Article title
Source
2022-11-21
Gulf Coast Sequestration and Climeworks Sign MOU to Develop First Direct Air Capture and Storage Hub on the Gulf Coast in Louisiana
2022-10-18
Gulf Coast Sequestration to locate first hub of its kind in SW La. for storing carbon dioxide emissions
2023-10-11
Gulf Coast Sequestration Appoints Industry Veteran David Cook as CEO; W. Gray Stream Named Executive Chairman
Data

Wells

Data for injection rates, perforation, and other well-related metrics.

GL CCS 1

Injection rate (Mt / year)
490,000
Injection years
15
Perforation intervals (feet)
10,273 to 10,324
Well class
Injector

GL CCS 2

Injection rate (Mt / year)
1,510,000
Injection years
15
Perforation intervals (feet)
11,012 to 11,213
Well class
Injector
Data

Geology

Subsurface data for carbon storage.

Upper Frio

Only injection formation is available.

Download

Project Documents

Technical, design, and planning materials outlining the project’s scope, development approach, and implementation details.

Download

Permitted Documents

Official approval, consent, and compliance documents issued by authorities, confirming the project is authorised to proceed.