Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Facility scope
EngineeringBechtel
Point source approachPost-Combustion Capture
CO₂ concentration6.0% mol%
Flue gas pressure—
Compressor nameplate—
Compression stages4
Compression inlet—
Compression discharge2,190 psia
Description
Bechtel National Inc., with the Electric Power Research Institute, is conducting a FEED study to retrofit Panda Power Funds’ 758 MWe natural gas combined cycle plant in Sherman, Texas, with a post-combustion CO₂ capture system. Using an open-access design and a conventional amine absorber-stripper system with a non-proprietary solvent such as MEA, the project targets CO₂ capture for enhanced oil recovery.
Scottish Power / Longannet Power Station
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
Facility scope
EngineeringAker Carbon Capture
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure—
Compressor nameplate—
Compression stages5
Compression inlet—
Compression discharge473 psia
Description
In March 2010, the Scottish CCS (Carbon Capture & Storage) Consortium began an extensive Front End, Engineering and Design (FEED) study to
assess what exactly would be required from an engineering, commercial and regulatory, perspective in order to progress the CCS demonstration project at Longannet Power station in Scotland (Goldeneye) through to construction. The study has yielded invaluable knowledge in areas such as cost, design, end-to-end CCS chain operation, health and safety, environment, consent and permitting, risk management, and lessons learnt.
Milton R. Young Power Plant
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Facility scope
EngineeringFluor
Point source approachPost-Combustion Capture
CO₂ concentration8.6% vol%
Flue gas pressure—
Compressor nameplate44.4 MW
Compression stages—
Compression inlet—
Compression discharge1,690 psia
Description
Milton R. Young Station Unit 2 is conducting a FEED study to add a post-combustion CO₂ capture system using Fluor’s Econamine FG Plus™ technology to its lignite-fueled power plant in North Dakota. The design targets 3.6 million tonnes of CO₂ captured annually—twice the scale of the largest existing facility—while integrating advanced heat recovery, aerosol and solvent degradation controls, and cold-climate optimization to achieve the lowest levelized cost of capture at world scale. The study will deliver detailed design, cost, and performance data for financing, permitting, and final project scheduling.