Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Rayburn Energy Station / Sherman Power Plant
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Facility scope
EngineeringBechtel
Point source approachPost-Combustion Capture
CO₂ concentration6.0% mol%
Flue gas pressure—
Compressor nameplate—
Compression stages4
Compression inlet—
Compression discharge2,190 psia
Description
Bechtel National Inc., with the Electric Power Research Institute, is conducting a FEED study to retrofit Panda Power Funds’ 758 MWe natural gas combined cycle plant in Sherman, Texas, with a post-combustion CO₂ capture system. Using an open-access design and a conventional amine absorber-stripper system with a non-proprietary solvent such as MEA, the project targets CO₂ capture for enhanced oil recovery.
Milton R. Young Power Plant
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Facility scope
EngineeringFluor
Point source approachPost-Combustion Capture
CO₂ concentration8.6% vol%
Flue gas pressure—
Compressor nameplate44.4 MW
Compression stages—
Compression inlet—
Compression discharge1,690 psia
Description
Milton R. Young Station Unit 2 is conducting a FEED study to add a post-combustion CO₂ capture system using Fluor’s Econamine FG Plus™ technology to its lignite-fueled power plant in North Dakota. The design targets 3.6 million tonnes of CO₂ captured annually—twice the scale of the largest existing facility—while integrating advanced heat recovery, aerosol and solvent degradation controls, and cold-climate optimization to achieve the lowest levelized cost of capture at world scale. The study will deliver detailed design, cost, and performance data for financing, permitting, and final project scheduling.
CLECO / Brame Energy Center Madison 3 Unit
CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
—MW
CO₂ concentration
14.1%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration14.1% vol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge2,015 psia
Description
Cleco Power (Cleco) performed a three-phase front-end engineering and design (FEED) study evaluating installation of a carbon dioxide (CO2) Capture System at Madison Unit 3 (MU3), Project Diamond Vault (DV) The work was performed under a Department of Energy (DOE) grant DE-FE0032165. The FEED study included three phases: (1) a feasibility phase which sought to define the scope of the project, (2) a pre-FEED phase which sought to develop a detailed cost estimate, and (3) a final FEED phase which sought to develop the project to be ready to move into execution. The FEED study was completed by Cleco, Mitsubishi Heavy Industries America (MHIA), and Sargent & Lundy, LLC (S&L) with oversight provided by the Louisiana Economic Development (LED). The feasibility phase was completed in February 2023, which was followed by the pre-FEED phase which concluded in January 2024. The project subsequently entered the final FEED phase, during this phase Cleco made the decision to stop work on the FEED study due to market conditions which resulted in a project that was not economically viable at the time.