Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Facility scope
EngineeringAECOM
Point source approachPost-Combustion Capture
CO₂ concentration3.8% vol%
Flue gas pressure14 psia
Compressor nameplate
Compression stages3
Compression inlet75 psia
Compression discharge2,015 psia
Description
The University of Texas at Austin, with AECOM Technical Services and Trimeric Corporation, is conducting a FEED study for the Piperazine Advanced Stripper (PZAS) CO₂ capture process at Golden Spread Electric Cooperative’s Mustang Station in Denver City, Texas. Designed for two GE gas turbines with HRSGs and a steam turbine totaling 464 MWe, the PZAS process uses 30 wt% piperazine for higher efficiency, solvent stability, smaller absorber size, and cost savings compared to conventional amine systems. The project will deliver a 30–60% complete design package and a capital cost estimate with ±15% accuracy.

Rayburn Energy Station / Sherman Power Plant

Natural GasFEED· Bechtel· 2022-03-01Project page ↗Cost report ↗
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Facility scope
EngineeringBechtel
Point source approachPost-Combustion Capture
CO₂ concentration6.0% mol%
Flue gas pressure
Compressor nameplate
Compression stages4
Compression inlet
Compression discharge2,190 psia
Description
Bechtel National Inc., with the Electric Power Research Institute, is conducting a FEED study to retrofit Panda Power Funds’ 758 MWe natural gas combined cycle plant in Sherman, Texas, with a post-combustion CO₂ capture system. Using an open-access design and a conventional amine absorber-stripper system with a non-proprietary solvent such as MEA, the project targets CO₂ capture for enhanced oil recovery.

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Facility scope
EngineeringKiewit
Point source approachPost-Combustion Capture
CO₂ concentration10.1% vol%
Flue gas pressure
Compressor nameplate
Compression stages7
Compression inlet
Compression discharge2,230 psia
Description
Electricore Inc., with Svante Inc. and Kiewit Engineering Group Inc., is conducting a pre-FEED study for a 1 million tonnes/year VeloxoTherm™ carbon capture system at LafargeHolcim’s cement plant in Florence, Colorado. The system will capture CO₂ from both kiln flue gas (14% concentration) and a natural gas-fired steam generator (8.5% concentration), with storage options including saline formations, depleted oil reservoirs, and the Sheep Mountain CO₂ reservoir. The study will also evaluate expansion to 2 million tonnes/year and target DOE’s $30/tonne capture cost goal, progressing from design selection (FEL-1) to pre-FEED engineering (FEL-2).