Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Mustang Station Power Plant
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Facility scope
EngineeringAECOM
Point source approachPost-Combustion Capture
CO₂ concentration3.8% vol%
Flue gas pressure14 psia
Compressor nameplate—
Compression stages3
Compression inlet75 psia
Compression discharge2,015 psia
Description
The University of Texas at Austin, with AECOM Technical Services and Trimeric Corporation, is conducting a FEED study for the Piperazine Advanced Stripper (PZAS) CO₂ capture process at Golden Spread Electric Cooperative’s Mustang Station in Denver City, Texas. Designed for two GE gas turbines with HRSGs and a steam turbine totaling 464 MWe, the PZAS process uses 30 wt% piperazine for higher efficiency, solvent stability, smaller absorber size, and cost savings compared to conventional amine systems. The project will deliver a 30–60% complete design package and a capital cost estimate with ±15% accuracy.
Calpine / Deer Park Energy Center
CO₂ captured
500,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
30.4MW
CO₂ concentration
5.2%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration5.2% vol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages5
Compression inlet—
Compression discharge2,215 psia
Description
Calpine Texas CCUS Holdings LLC, with Electricore Inc., is conducting a FEED study for a modular post-combustion CO₂ capture system at the Deer Park Energy Center NGCC plant in Texas. Using Shell’s commercial-scale amine technology, the system will capture 95% of emissions—about 5 MTPA—while maintaining low energy use and fast reaction rates. The study will include business case, techno-economic, life cycle, environmental, and public policy analyses, including environmental justice and job creation impacts.
Holcim / Portland Cement Plant
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Facility scope
EngineeringKiewit
Point source approachPost-Combustion Capture
CO₂ concentration10.1% vol%
Flue gas pressure—
Compressor nameplate—
Compression stages7
Compression inlet—
Compression discharge2,230 psia
Description
Electricore Inc., with Svante Inc. and Kiewit Engineering Group Inc., is conducting a pre-FEED study for a 1 million tonnes/year VeloxoTherm™ carbon capture system at LafargeHolcim’s cement plant in Florence, Colorado. The system will capture CO₂ from both kiln flue gas (14% concentration) and a natural gas-fired steam generator (8.5% concentration), with storage options including saline formations, depleted oil reservoirs, and the Sheep Mountain CO₂ reservoir. The study will also evaluate expansion to 2 million tonnes/year and target DOE’s $30/tonne capture cost goal, progressing from design selection (FEL-1) to pre-FEED engineering (FEL-2).