Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Facility scope
EngineeringTrimeric
Point source approachPost-Combustion Capture
CO₂ concentration12.5% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages6
Compression inlet6 psia
Compression discharge2,219 psia
Description
Membrane Technology and Research Inc., with Technology Centre Mongstad, Dresser-Rand, Trimeric Corporation, and WorleyParsons/Advisian, is scaling up its advanced Polaris™ membranes for post-combustion CO₂ capture and testing them at engineering scale at TCM in Norway. The Polaris membranes, about 20 times more permeable than prior commercial versions, use a patented selective recycle design to boost CO₂ concentration in flue gas and lower capture costs. The project will design, build, and operate a modular membrane system for a six-month field test, including performance verification, steady-state operation, techno-economic updates, and integration studies with advanced compression technology.

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Facility scope
EngineeringHTC Puretech
Point source approachPost-Combustion Capture
CO₂ concentration8.6% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge
Description
A Front End Engineering and Design (FEED) study was undertaken to design an advanced CO2 Capture Unit (CCU) to produce 1000 tonnes per day of CO2 from the exhaust of three Once-Through Steam Generators (OTSG’s) at Devon Energy’s Jackfish 1 thermal in-situ operations and estimate the capital expenditure for the facilities within +/-15% accuracy. The process utilizes HTC Purenergy Carbon Capture Technology to capture CO2 from the OTSG exhaust gas using an aqueous chemical solvent in an absorber tower, after which the CO2-loaded solvent is passed to a stripper tower where the CO2 is released and the solvent regenerated. The study excludes downstream CO2 compression, dehydration, transportation and storage.

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Facility scope
EngineeringKiewit
Point source approachPost-Combustion Capture
CO₂ concentration10.1% vol%
Flue gas pressure
Compressor nameplate
Compression stages7
Compression inlet
Compression discharge2,230 psia
Description
Electricore Inc., with Svante Inc. and Kiewit Engineering Group Inc., is conducting a pre-FEED study for a 1 million tonnes/year VeloxoTherm™ carbon capture system at LafargeHolcim’s cement plant in Florence, Colorado. The system will capture CO₂ from both kiln flue gas (14% concentration) and a natural gas-fired steam generator (8.5% concentration), with storage options including saline formations, depleted oil reservoirs, and the Sheep Mountain CO₂ reservoir. The study will also evaluate expansion to 2 million tonnes/year and target DOE’s $30/tonne capture cost goal, progressing from design selection (FEL-1) to pre-FEED engineering (FEL-2).