Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Technology Centre Mongstad

CoalLarge Pilot· Membrane Technology and Research (MTR)· 2023-08-15Project page ↗Cost report ↗
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Facility scope
EngineeringTrimeric
Point source approachPost-Combustion Capture
CO₂ concentration12.5% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages6
Compression inlet6 psia
Compression discharge2,219 psia
Description
Membrane Technology and Research Inc., with Technology Centre Mongstad, Dresser-Rand, Trimeric Corporation, and WorleyParsons/Advisian, is scaling up its advanced Polaris™ membranes for post-combustion CO₂ capture and testing them at engineering scale at TCM in Norway. The Polaris membranes, about 20 times more permeable than prior commercial versions, use a patented selective recycle design to boost CO₂ concentration in flue gas and lower capture costs. The project will design, build, and operate a modular membrane system for a six-month field test, including performance verification, steady-state operation, techno-economic updates, and integration studies with advanced compression technology.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Facility scope
EngineeringSargent and Lundy
Point source approachPost-Combustion Capture
CO₂ concentration12.8% mol%
Flue gas pressure14 psia
Compressor nameplate46 MW
Compression stages5
Compression inlet
Compression discharge2,215 psia
Description
The CEMEX Balcones Carbon Capture project is a DOE-supported Front-End Engineering Design (FEED) study evaluating commercial-scale deployment of RTI International’s non-aqueous solvent (NAS) technology at the Balcones cement plant in New Braunfels, Texas. The study assessed capture of approximately 2.4 million tonnes of CO₂ per year at roughly 95% capture efficiency from cement kiln flue gas and an associated natural gas–fired boiler, developing an AACE Class 3 cost estimate and detailed engineering design to support future investment decisions. Led by RTI International with KBR as EPC engineering contractor and SLB Capturi as owner’s engineer and technology licensor, the project evaluated integration challenges such as limited cooling water availability, resulting in a hybrid air- and water-cooling configuration. The FEED estimated total project capital costs of about $849 million and annual operating costs of approximately $109 million, providing a techno-economic basis for large-scale cement decarbonization and future project execution planning.

Southern Company / Plant Daniel

Natural GasFEED· Southern Company· 2022-11-30Project page ↗Cost report ↗
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
79MW
CO₂ concentration
Facility scope
EngineeringLinde Engineering (ISBL), Southern Company Services (OSBL)
Point source approachPost-Combustion Capture
CO₂ concentration
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge
Description
Southern Company Services, with Linde Gas North America, is conducting a FEED study for a commercial-scale CO₂ capture system using Linde-BASF’s advanced aqueous amine technology at an NGCC plant of at least 375 MWe. The project will evaluate Alabama Power’s Plant Barry and Mississippi Power’s Plant Daniel to select the optimal host site, define project requirements, optimize process design, and deliver engineering packages along with a cost and schedule estimate within 15% accuracy. The study will build on prior feasibility work and site-specific testing.