Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Calpine / Deer Park Energy Center
CO₂ captured
6,200,000t/yr
Capture efficiency
95.0%
Utilization
90.0%
Parasitic load
184MW
CO₂ concentration
5.2%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration5.2% vol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages8
Compression inlet—
Compression discharge2,215 psia
Description
Calpine Texas CCUS Holdings LLC, with Electricore Inc., is conducting a FEED study for a modular post-combustion CO₂ capture system at the Deer Park Energy Center NGCC plant in Texas. Using Shell’s commercial-scale amine technology, the system will capture 95% of emissions—about 5 MTPA—while maintaining low energy use and fast reaction rates. The study will include business case, techno-economic, life cycle, environmental, and public policy analyses, including environmental justice and job creation impacts.
Mustang Station Power Plant
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Facility scope
EngineeringAECOM
Point source approachPost-Combustion Capture
CO₂ concentration3.8% vol%
Flue gas pressure14 psia
Compressor nameplate—
Compression stages3
Compression inlet75 psia
Compression discharge2,015 psia
Description
The University of Texas at Austin, with AECOM Technical Services and Trimeric Corporation, is conducting a FEED study for the Piperazine Advanced Stripper (PZAS) CO₂ capture process at Golden Spread Electric Cooperative’s Mustang Station in Denver City, Texas. Designed for two GE gas turbines with HRSGs and a steam turbine totaling 464 MWe, the PZAS process uses 30 wt% piperazine for higher efficiency, solvent stability, smaller absorber size, and cost savings compared to conventional amine systems. The project will deliver a 30–60% complete design package and a capital cost estimate with ±15% accuracy.
Scottish Power / Longannet Power Station
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
Facility scope
EngineeringAker Carbon Capture
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure—
Compressor nameplate—
Compression stages5
Compression inlet—
Compression discharge473 psia
Description
In March 2010, the Scottish CCS (Carbon Capture & Storage) Consortium began an extensive Front End, Engineering and Design (FEED) study to
assess what exactly would be required from an engineering, commercial and regulatory, perspective in order to progress the CCS demonstration project at Longannet Power station in Scotland (Goldeneye) through to construction. The study has yielded invaluable knowledge in areas such as cost, design, end-to-end CCS chain operation, health and safety, environment, consent and permitting, risk management, and lessons learnt.