Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Facility scope
EngineeringTrimeric
Point source approachCompression and Dehydration
CO₂ concentration99.0% vol%
Flue gas pressure
Compressor nameplate8.7 MW
Compression stages8
Compression inlet30 psia
Compression discharge1,514 psia
Description
This report summarizes Trimeric’s Phase II work under the SSEB ECO2S project in Kemper County, Mississippi, focused on Task 7 – Infrastructure Development. Trimeric evaluated CO₂ compression and dehydration costs, compared pumping versus compression for dense phase CO₂, and developed pipeline transport cost estimates. Using experience from past projects, screening-level designs and cost estimates were prepared for a nominal 1 MTPY case and scaled to site-specific conditions. Results showed that increasing discharge pressure modestly raises costs, with pumping offering slight savings and operational flexibility but added complexity. Pipeline costs were estimated using NPC benchmarks, while compression and dehydration costs were scaled for Plant Daniel, Plant Miller, and Kemper. Overall, capital costs were roughly three times equipment costs, with electricity for compression as the dominant operating expense. The costs are associated with 8-stage compression to 1,500 psig.

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEED· Dastur International· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
79MW
CO₂ concentration
21.9%vol%
Facility scope
EngineeringDastur International
Point source approachPost-Combustion Capture
CO₂ concentration21.9% vol%
Flue gas pressure17 psia
Compressor nameplate
Compression stages6
Compression inlet
Compression discharge2,215 psia
Description
Dastur International Inc., with Cleveland-Cliffs Inc., is designing a carbon capture system for the 5 mtpa integrated steel plant in Burns Harbor, Indiana, to capture 50–70% of CO₂ emissions from blast furnace gas. The system will combine a gas flow distribution network, a specialized conditioning process, and ION Clean Energy’s solvent-based capture technology with 90–98% efficiency, with water-gas shift reactors enabling higher capture rates. Dastur will lead overall plant integration and engineering, while ION designs the capture island and Dastur Energy optimizes design and energy performance.

Holcim / Portland Cement Plant

Cementpre-FEED· Electricore· 2023-01-31Project page ↗Cost report ↗
CO₂ captured
1,733,750t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
76MW
CO₂ concentration
10.1%vol%
Facility scope
EngineeringKiewit
Point source approachPost-Combustion Capture
CO₂ concentration10.1% vol%
Flue gas pressure
Compressor nameplate
Compression stages7
Compression inlet
Compression discharge2,230 psia
Description
Electricore Inc., with Svante Inc. and Kiewit Engineering Group Inc., is conducting a pre-FEED study for a 1 million tonnes/year VeloxoTherm™ carbon capture system at LafargeHolcim’s cement plant in Florence, Colorado. The system will capture CO₂ from both kiln flue gas (14% concentration) and a natural gas-fired steam generator (8.5% concentration), with storage options including saline formations, depleted oil reservoirs, and the Sheep Mountain CO₂ reservoir. The study will also evaluate expansion to 2 million tonnes/year and target DOE’s $30/tonne capture cost goal, progressing from design selection (FEL-1) to pre-FEED engineering (FEL-2).