Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
4,200,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Facility scope
EngineeringTrimeric
Point source approachCompression and Dehydration
CO₂ concentration99.0% vol%
Flue gas pressure
Compressor nameplate43.3 MW
Compression stages8
Compression inlet30 psia
Compression discharge1,515 psia
Description
This report summarizes Trimeric’s Phase II work under the SSEB ECO2S project in Kemper County, Mississippi, focused on Task 7 – Infrastructure Development. Trimeric evaluated CO₂ compression and dehydration costs, compared pumping versus compression for dense phase CO₂, and developed pipeline transport cost estimates. Using experience from past projects, screening-level designs and cost estimates were prepared for a nominal 1 MTPY case and scaled to site-specific conditions. Results showed that increasing discharge pressure modestly raises costs, with pumping offering slight savings and operational flexibility but added complexity. Pipeline costs were estimated using NPC benchmarks, while compression and dehydration costs were scaled for Plant Daniel, Plant Miller, and Kemper. Overall, capital costs were roughly three times equipment costs, with electricity for compression as the dominant operating expense. The costs are associated with 8-stage compression to 1,500 psig

Mustang Station Power Plant

Natural GasFEED· University of Texas at Austin· 2022-01-07Project page ↗Cost report ↗
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Facility scope
EngineeringAECOM
Point source approachPost-Combustion Capture
CO₂ concentration3.8% vol%
Flue gas pressure14 psia
Compressor nameplate
Compression stages3
Compression inlet75 psia
Compression discharge2,015 psia
Description
The University of Texas at Austin, with AECOM Technical Services and Trimeric Corporation, is conducting a FEED study for the Piperazine Advanced Stripper (PZAS) CO₂ capture process at Golden Spread Electric Cooperative’s Mustang Station in Denver City, Texas. Designed for two GE gas turbines with HRSGs and a steam turbine totaling 464 MWe, the PZAS process uses 30 wt% piperazine for higher efficiency, solvent stability, smaller absorber size, and cost savings compared to conventional amine systems. The project will deliver a 30–60% complete design package and a capital cost estimate with ±15% accuracy.

Finnish Integrated Pulp and Board Mill / Capture of CO2 in the Lime Kiln only

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
197,008t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
2.8MW
CO₂ concentration
27.6%mol%
Facility scope
Engineering
Point source approachPost-Combustion Capture
CO₂ concentration27.6% mol%
Flue gas pressure
Compressor nameplate
Compression stages4
Compression inlet
Compression discharge1,595 psia
Description
Analysis sets the design and cost-estimating basis for evaluating pulp and board mills with and without CCS. Two base cases are considered: a market pulp mill and an integrated pulp and board mill. Six CCS cases are evaluated, capturing CO₂ from the recovery boiler, multi-fuel boiler, lime kiln, or their combinations. The mills are assumed to be energy independent, with black liquor and bark burned to produce steam and electricity, and excess electricity exported to the grid. The CO₂ capture system uses post-combustion MEA technology with a 90% capture rate, and if on-site electricity is insufficient, an auxiliary boiler firing forest residues will supply the additional energy. Capture of CO2 in the Lime Kiln only