Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Southern Company / Plant Barry
CO₂ captured
4,200,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
CO₂ concentration
99.0%vol%
Facility scope
EngineeringTrimeric
Point source approachCompression and Dehydration
CO₂ concentration99.0% vol%
Flue gas pressure—
Compressor nameplate45 MW
Compression stages6
Compression inlet30 psia
Compression discharge2,065 psia
Description
This report summarizes Trimeric’s Phase II work under the SSEB ECO2S project in Kemper County, Mississippi, focused on Task 7 – Infrastructure Development. Trimeric evaluated CO₂ compression and dehydration costs, compared pumping versus compression for dense phase CO₂, and developed pipeline transport cost estimates. Using experience from past projects, screening-level designs and cost estimates were prepared for a nominal 1 MTPY case and scaled to site-specific conditions. Results showed that increasing discharge pressure modestly raises costs, with pumping offering slight savings and operational flexibility but added complexity. Pipeline costs were estimated using NPC benchmarks, while compression and dehydration costs were scaled for Plant Daniel, Plant Miller, and Kemper. Overall, capital costs were roughly three times equipment costs, with electricity for compression as the dominant operating expense. The costs are associated with Six-stage compression directly to 2,050 psig
Finnish Market Pulp Mill / Capture of CO2 in both Kraft Boiler & Lime Kiln
Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,675,922t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
26.9MW
CO₂ concentration
15.5%mol%
Facility scope
Engineering—
Point source approachPost-Combustion Capture
CO₂ concentration15.5% mol%
Flue gas pressure—
Compressor nameplate—
Compression stages4
Compression inlet—
Compression discharge1,595 psia
Description
Analysis sets the design and cost-estimating basis for evaluating pulp and board mills with and without CCS. Two base cases are considered: a market pulp mill and an integrated pulp and board mill. Six CCS cases are evaluated, capturing CO₂ from the recovery boiler, multi-fuel boiler, lime kiln, or their combinations. The mills are assumed to be energy independent, with black liquor and bark burned to produce steam and electricity, and excess electricity exported to the grid. The CO₂ capture system uses post-combustion MEA technology with a 90% capture rate, and if on-site electricity is insufficient, an auxiliary boiler firing forest residues will supply the additional energy. Capture of CO2 in both Kraft Boiler & Lime Kiln
CEMEX / Balcones Cement Plant
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
—MW
CO₂ concentration
12.8%mol%
Facility scope
EngineeringSargent and Lundy
Point source approachPost-Combustion Capture
CO₂ concentration12.8% mol%
Flue gas pressure14 psia
Compressor nameplate46 MW
Compression stages5
Compression inlet—
Compression discharge2,215 psia
Description
The CEMEX Balcones Carbon Capture project is a DOE-supported Front-End Engineering Design (FEED) study evaluating commercial-scale deployment of RTI International’s non-aqueous solvent (NAS) technology at the Balcones cement plant in New Braunfels, Texas. The study assessed capture of approximately 2.4 million tonnes of CO₂ per year at roughly 95% capture efficiency from cement kiln flue gas and an associated natural gas–fired boiler, developing an AACE Class 3 cost estimate and detailed engineering design to support future investment decisions. Led by RTI International with KBR as EPC engineering contractor and SLB Capturi as owner’s engineer and technology licensor, the project evaluated integration challenges such as limited cooling water availability, resulting in a hybrid air- and water-cooling configuration. The FEED estimated total project capital costs of about $849 million and annual operating costs of approximately $109 million, providing a techno-economic basis for large-scale cement decarbonization and future project execution planning.