Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CLECO / Brame Energy Center Madison 3 Unit

CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
MW
CO₂ concentration
14.1%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration14.1% vol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,015 psia
Description
Cleco Power (Cleco) performed a three-phase front-end engineering and design (FEED) study evaluating installation of a carbon dioxide (CO2) Capture System at Madison Unit 3 (MU3), Project Diamond Vault (DV) The work was performed under a Department of Energy (DOE) grant DE-FE0032165. The FEED study included three phases: (1) a feasibility phase which sought to define the scope of the project, (2) a pre-FEED phase which sought to develop a detailed cost estimate, and (3) a final FEED phase which sought to develop the project to be ready to move into execution. The FEED study was completed by Cleco, Mitsubishi Heavy Industries America (MHIA), and Sargent & Lundy, LLC (S&L) with oversight provided by the Louisiana Economic Development (LED). The feasibility phase was completed in February 2023, which was followed by the pre-FEED phase which concluded in January 2024. The project subsequently entered the final FEED phase, during this phase Cleco made the decision to stop work on the FEED study due to market conditions which resulted in a project that was not economically viable at the time.

Southern Company / Plant Barry

Natural GasFEED· GE Gas Power· 2024-08-06Project page ↗Cost report ↗
CO₂ captured
1,632,000t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
18.4MW
CO₂ concentration
6.7%mol%
Facility scope
EngineeringLinde Engineering (process engineering and equipment cost), Kiewit (plant layout, constructability, installation)
Point source approachPost-Combustion Capture
CO₂ concentration6.7% mol%
Flue gas pressure14 psia
Compressor nameplate20.8 MW
Compression stages
Compression inlet
Compression discharge2,215 psia
Description
General Electric Gas Power, with Linde, Kiewit, and Southern Company Services, is conducting a FEED study for a “Generation 2” amine-based post-combustion CO₂ capture system at an existing NGCC power plant. Targeting at least 95% capture efficiency, the design will emphasize optimized integration, lower CCS costs, and flexible operation to complement renewable energy. The 18-month project will progress from multiple conceptual designs to a single configuration, culminating in a detailed design, technical viability assessment, techno-economic and life cycle analyses, and a business case evaluation.

Rayburn Energy Station / Sherman Power Plant

Natural GasFEED· Bechtel· 2022-03-01Project page ↗Cost report ↗
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Facility scope
EngineeringBechtel
Point source approachPost-Combustion Capture
CO₂ concentration6.0% mol%
Flue gas pressure
Compressor nameplate
Compression stages4
Compression inlet
Compression discharge2,190 psia
Description
Bechtel National Inc., with the Electric Power Research Institute, is conducting a FEED study to retrofit Panda Power Funds’ 758 MWe natural gas combined cycle plant in Sherman, Texas, with a post-combustion CO₂ capture system. Using an open-access design and a conventional amine absorber-stripper system with a non-proprietary solvent such as MEA, the project targets CO₂ capture for enhanced oil recovery.