Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Scottish Power / Longannet Power Station
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
Facility scope
EngineeringAker Carbon Capture
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure—
Compressor nameplate—
Compression stages5
Compression inlet—
Compression discharge473 psia
Description
In March 2010, the Scottish CCS (Carbon Capture & Storage) Consortium began an extensive Front End, Engineering and Design (FEED) study to
assess what exactly would be required from an engineering, commercial and regulatory, perspective in order to progress the CCS demonstration project at Longannet Power station in Scotland (Goldeneye) through to construction. The study has yielded invaluable knowledge in areas such as cost, design, end-to-end CCS chain operation, health and safety, environment, consent and permitting, risk management, and lessons learnt.
Linde Hydrogen Plant
CO₂ captured
1,360,000t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
18.3%mol%
Facility scope
EngineeringLinde Engineering
Point source approachPost-Combustion Capture
CO₂ concentration18.3% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
Linde Inc., with Linde Engineering Americas and BASF, is conducting an initial engineering design for a 3,500 tonnes/day CO₂ capture plant using Linde-BASF’s advanced aqueous amine technology at a Linde-owned steam methane reforming facility. The project will define integration options, establish project requirements, optimize process design, and develop engineering, cost, and schedule packages. BASF will provide the technology design, LEA will deliver detailed engineering and constructability assessments, and Linde will lead techno-economic, environmental, and safety analyses in coordination with the SMR plant operators.
Devon Energy / Jackfish-1 Oil Sands
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
8.6%mol%
Facility scope
EngineeringHTC Puretech
Point source approachPost-Combustion Capture
CO₂ concentration8.6% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
A Front End Engineering and Design (FEED) study was undertaken to design an advanced CO2 Capture
Unit (CCU) to produce 1000 tonnes per day of CO2 from the exhaust of three Once-Through Steam
Generators (OTSG’s) at Devon Energy’s Jackfish 1 thermal in-situ operations and estimate the capital
expenditure for the facilities within +/-15% accuracy.
The process utilizes HTC Purenergy Carbon Capture Technology to capture CO2 from the OTSG exhaust
gas using an aqueous chemical solvent in an absorber tower, after which the CO2-loaded solvent is
passed to a stripper tower where the CO2 is released and the solvent regenerated. The study excludes
downstream CO2 compression, dehydration, transportation and storage.