Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Nutrien Redwater Nitrogen Operations
CO₂ captured
747,155t/yr
Capture efficiency
95.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge2,614 psia
Description
CO₂ capture from the SMR flue gas stacks located in Plant 01 and Plant 09 of the facility. Combined flue gases from each of the two sources would be collected and transported by ducts to the carbon capture facility. The design of the capture facility is 2,100 – 2,200 tpd of CO₂, including the CO₂ captured from the SMRs and additional flue gas generated from the steam boiler supplying the CCS unit. The CCS unit is to be designed for a minimum 30% plant turndown, this is to ensure the operation of CCS unit when flue gas from Plant 01 is the only feed to the CCS unit. For the purposes of the study the carbon capture facility design, including flue gas pretreatment and downstream CO₂ compression and dehydration, is provided by licensor. Hatch designed the flue gas transportation from the stacks to the Carbon Capture and Sequestration (CCS) unit battery limit, flue gas pressure boosting and Balance of Plant (BOP) which includes all the utility and offsite systems
Technology Centre Mongstad
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Facility scope
EngineeringTrimeric
Point source approachPost-Combustion Capture
CO₂ concentration12.5% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages6
Compression inlet6 psia
Compression discharge2,219 psia
Description
Membrane Technology and Research Inc., with Technology Centre Mongstad, Dresser-Rand, Trimeric Corporation, and WorleyParsons/Advisian, is scaling up its advanced Polaris™ membranes for post-combustion CO₂ capture and testing them at engineering scale at TCM in Norway. The Polaris membranes, about 20 times more permeable than prior commercial versions, use a patented selective recycle design to boost CO₂ concentration in flue gas and lower capture costs. The project will design, build, and operate a modular membrane system for a six-month field test, including performance verification, steady-state operation, techno-economic updates, and integration studies with advanced compression technology.
Mustang Station Power Plant
CO₂ captured
853,644t/yr
Capture efficiency
90.0%
Utilization
52.0%
Parasitic load
46MW
CO₂ concentration
3.8%vol%
Facility scope
EngineeringAECOM
Point source approachPost-Combustion Capture
CO₂ concentration3.8% vol%
Flue gas pressure14 psia
Compressor nameplate—
Compression stages3
Compression inlet75 psia
Compression discharge2,015 psia
Description
The University of Texas at Austin, with AECOM Technical Services and Trimeric Corporation, is conducting a FEED study for the Piperazine Advanced Stripper (PZAS) CO₂ capture process at Golden Spread Electric Cooperative’s Mustang Station in Denver City, Texas. Designed for two GE gas turbines with HRSGs and a steam turbine totaling 464 MWe, the PZAS process uses 30 wt% piperazine for higher efficiency, solvent stability, smaller absorber size, and cost savings compared to conventional amine systems. The project will deliver a 30–60% complete design package and a capital cost estimate with ±15% accuracy.