Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
747,155t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,614 psia
Description
CO₂ capture from the SMR flue gas stacks located in Plant 01 and Plant 09 of the facility. Combined flue gases from each of the two sources would be collected and transported by ducts to the carbon capture facility. The design of the capture facility is 2,100 – 2,200 tpd of CO₂, including the CO₂ captured from the SMRs and additional flue gas generated from the steam boiler supplying the CCS unit. The CCS unit is to be designed for a minimum 30% plant turndown, this is to ensure the operation of CCS unit when flue gas from Plant 01 is the only feed to the CCS unit. For the purposes of the study the carbon capture facility design, including flue gas pretreatment and downstream CO₂ compression and dehydration, is provided by licensor. Hatch designed the flue gas transportation from the stacks to the Carbon Capture and Sequestration (CCS) unit battery limit, flue gas pressure boosting and Balance of Plant (BOP) which includes all the utility and offsite systems

Southern Company / Plant Barry

Compression and Dehydration· Trimeric· 2020-02-01Project page ↗Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
Utilization
95.0%
Parasitic load
MW
CO₂ concentration
99.0%vol%
Facility scope
EngineeringTrimeric
Point source approachCompression and Dehydration
CO₂ concentration99.0% vol%
Flue gas pressure
Compressor nameplate24.8 MW
Compression stages6
Compression inlet30 psia
Compression discharge2,065 psia
Description
This report summarizes Trimeric’s Phase II work under the SSEB ECO2S project in Kemper County, Mississippi, focused on Task 7 – Infrastructure Development. Trimeric evaluated CO₂ compression and dehydration costs, compared pumping versus compression for dense phase CO₂, and developed pipeline transport cost estimates. Using experience from past projects, screening-level designs and cost estimates were prepared for a nominal 1 MTPY case and scaled to site-specific conditions. Results showed that increasing discharge pressure modestly raises costs, with pumping offering slight savings and operational flexibility but added complexity. Pipeline costs were estimated using NPC benchmarks, while compression and dehydration costs were scaled for Plant Daniel, Plant Miller, and Kemper. Overall, capital costs were roughly three times equipment costs, with electricity for compression as the dominant operating expense. The costs are associated with Six-stage compression to 1,500 psig, followed by pumping to 2,050 psig

CEMEX / Balcones Cement Plant

Cementpre-FEED· Membrane Technology and Research (MTR)· 2022-06-03Project page ↗Cost report ↗
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration14.9% vol%
Flue gas pressure14 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,213 psia
Description
Membrane Technology & Research Inc., with Sargent & Lundy and CEMEX, is designing a full-scale Polaris membrane CO₂ capture system for the CEMEX Balcones cement plant in New Braunfels, Texas, targeting about 1 million tonnes of CO₂ capture annually. The study will develop the design basis, process design, cost estimates, permitting and safety reviews, constructability assessment, and a techno-economic analysis. Sargent & Lundy will lead the design work, while CEMEX will provide site-specific data for integration.