Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,614 psia
Description
Studied the replacement of the SMR units with auto-thermal reforming (ATR) technology. ATRs produce a high concentration CO₂ stream, instead of low concentration combustion flue gases, that is more efficient to capture for sequestration. H₂ production from the unit may also be oversized to provide H₂ as a fuel source for the ATR if target overall CO₂ recovery of the facility is not achieved with the replacement of the SMR alone. The facility capacity is based on the total H₂ production requirements of the existing Plant 01 and Plant 09 ammonia synthesis units. 3 | P a g e Public – Approved for external distribution The scope for the study involves the SMR unit replacement with an integrated ATR and downstream syngas purification including CO₂ capture. The project scope also includes an Air Separation Unit (ASU) to supply oxygen to the ATR unit.

Holcim / Ste. Genevieve Cement Plant

CementFEED· University of Illinois· 2024-08-29Project page ↗Cost report ↗
CO₂ captured
3,056,339t/yr
Capture efficiency
95.0%
Utilization
85.0%
Parasitic load
60MW
CO₂ concentration
20.3%mol%
Facility scope
EngineeringKiewit
Point source approachPost-Combustion Capture
CO₂ concentration20.3% mol%
Flue gas pressure16 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,215 psia
Description
The University of Illinois at Urbana-Champaign is leading a FEED study for a commercial-scale CO₂ capture system at Holcim’s Ste. Genevieve cement plant in Missouri, targeting 95% capture efficiency. Using Air Liquide’s Cryocap™ technology, which combines PSA pre-concentration with cryogenic purification, the system will produce high-purity CO₂ for storage near the Prairie State Generating Company in Illinois. UIUC will manage the project and perform economic and impact analyses, while Air Liquide, Kiewit, Visage Energy, and Holcim will contribute to design, safety, environmental, and site integration efforts.

Cleveland Cliffs / Burns Harbor

Iron and Steelpre-FEED· Dastur International· 2023-03-01Project page ↗Cost report ↗
CO₂ captured
2,800,000t/yr
Capture efficiency
95.0%
Utilization
Parasitic load
79MW
CO₂ concentration
21.9%vol%
Facility scope
EngineeringDastur International
Point source approachPost-Combustion Capture
CO₂ concentration21.9% vol%
Flue gas pressure17 psia
Compressor nameplate
Compression stages6
Compression inlet
Compression discharge2,215 psia
Description
Dastur International Inc., with Cleveland-Cliffs Inc., is designing a carbon capture system for the 5 mtpa integrated steel plant in Burns Harbor, Indiana, to capture 50–70% of CO₂ emissions from blast furnace gas. The system will combine a gas flow distribution network, a specialized conditioning process, and ION Clean Energy’s solvent-based capture technology with 90–98% efficiency, with water-gas shift reactors enabling higher capture rates. Dastur will lead overall plant integration and engineering, while ION designs the capture island and Dastur Energy optimizes design and energy performance.