Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Nutrien Redwater Nitrogen Operations
CO₂ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge2,614 psia
Description
Studied the replacement of the SMR units with auto-thermal reforming (ATR) technology. ATRs produce a high concentration CO₂ stream, instead of low concentration combustion flue gases, that is more efficient to capture for sequestration. H₂ production from the unit may also be oversized to provide H₂ as a fuel source for the ATR if target overall CO₂ recovery of the facility is not achieved with the replacement of the SMR alone. The facility capacity is based on the total H₂ production requirements of the existing Plant 01 and Plant 09 ammonia synthesis units. 3 | P a g e Public – Approved for external distribution The scope for the study involves the SMR unit replacement with an integrated ATR and downstream syngas purification including CO₂ capture. The project scope also includes an Air Separation Unit (ASU) to supply oxygen to the ATR unit.
Technology Centre Mongstad
CO₂ captured
5,658,960t/yr
Capture efficiency
70.0%
Utilization
85.0%
Parasitic load
182MW
CO₂ concentration
12.5%mol%
Facility scope
EngineeringTrimeric
Point source approachPost-Combustion Capture
CO₂ concentration12.5% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages6
Compression inlet6 psia
Compression discharge2,219 psia
Description
Membrane Technology and Research Inc., with Technology Centre Mongstad, Dresser-Rand, Trimeric Corporation, and WorleyParsons/Advisian, is scaling up its advanced Polaris™ membranes for post-combustion CO₂ capture and testing them at engineering scale at TCM in Norway. The Polaris membranes, about 20 times more permeable than prior commercial versions, use a patented selective recycle design to boost CO₂ concentration in flue gas and lower capture costs. The project will design, build, and operate a modular membrane system for a six-month field test, including performance verification, steady-state operation, techno-economic updates, and integration studies with advanced compression technology.
Milton R. Young Power Plant
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Facility scope
EngineeringFluor
Point source approachPost-Combustion Capture
CO₂ concentration8.6% vol%
Flue gas pressure—
Compressor nameplate44.4 MW
Compression stages—
Compression inlet—
Compression discharge1,690 psia
Description
Milton R. Young Station Unit 2 is conducting a FEED study to add a post-combustion CO₂ capture system using Fluor’s Econamine FG Plus™ technology to its lignite-fueled power plant in North Dakota. The design targets 3.6 million tonnes of CO₂ captured annually—twice the scale of the largest existing facility—while integrating advanced heat recovery, aerosol and solvent degradation controls, and cold-climate optimization to achieve the lowest levelized cost of capture at world scale. The study will deliver detailed design, cost, and performance data for financing, permitting, and final project scheduling.