Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,614 psia
Description
Scope starts with the receipt of natural gas and fuel gas mixture from the existing Plant 01 and Plant 09 source and terminates with hydrogen (H₂) at the required specification and conditions to be used as fuel in the existing SMR unit. High concentration CO₂ from the ATR is captured and H₂ production from the proposed facility will replace the fuel gas feed to the primary reformer for heating. The facility capacity is based on the heating duty required to replace the current fuel source. The scope for the study involves the new ATR unit and associated downstream shift, CO₂ capture, and syngas purification unit. The project scope also includes an ASU to supply oxygen to the ATR unit.

CLECO / Brame Energy Center Madison 3 Unit

CoalFEED· Cleco Power· 2025-03-25
CO₂ captured
4,280,000t/yr
Capture efficiency
95.0%
Utilization
80.0%
Parasitic load
MW
CO₂ concentration
14.1%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration14.1% vol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,015 psia
Description
Cleco Power (Cleco) performed a three-phase front-end engineering and design (FEED) study evaluating installation of a carbon dioxide (CO2) Capture System at Madison Unit 3 (MU3), Project Diamond Vault (DV) The work was performed under a Department of Energy (DOE) grant DE-FE0032165. The FEED study included three phases: (1) a feasibility phase which sought to define the scope of the project, (2) a pre-FEED phase which sought to develop a detailed cost estimate, and (3) a final FEED phase which sought to develop the project to be ready to move into execution. The FEED study was completed by Cleco, Mitsubishi Heavy Industries America (MHIA), and Sargent & Lundy, LLC (S&L) with oversight provided by the Louisiana Economic Development (LED). The feasibility phase was completed in February 2023, which was followed by the pre-FEED phase which concluded in January 2024. The project subsequently entered the final FEED phase, during this phase Cleco made the decision to stop work on the FEED study due to market conditions which resulted in a project that was not economically viable at the time.

Linde / Port Arthur Facility

Hydrogenpre-FEED· Linde· 2023-12-04Project page ↗Cost report ↗
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
MW
CO₂ concentration
16.2%mol%
Facility scope
EngineeringKiewit (EPC costs for Svante’s equipment, steam generators, and OSBL construction), Linde (EPC costs for CO₂ purification/compression and EP costs for OSBL utilities)
Point source approachPost-Combustion Capture
CO₂ concentration16.2% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge
Description
Linde Inc., with Linde Engineering Americas, Linde Engineering Dresden, and Svante Inc., is completing an initial engineering design for a commercial-scale CO₂ capture plant at its steam methane reforming hydrogen facility in Port Arthur, Texas. Using Svante’s VeloxoTherm™ solid adsorbent technology, the system will capture about 1 million tonnes of CO₂ annually at ≥90% efficiency while producing 99.97% pure “blue” hydrogen. The design will include ISBL units for flue gas conditioning and CO₂ purification, OSBL components, and a techno-economic analysis of capture costs and hydrogen production economics.