Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Devon Energy / Jackfish-1 Oil Sands
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
8.6%mol%
Facility scope
EngineeringHTC Puretech
Point source approachPost-Combustion Capture
CO₂ concentration8.6% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
A Front End Engineering and Design (FEED) study was undertaken to design an advanced CO2 Capture
Unit (CCU) to produce 1000 tonnes per day of CO2 from the exhaust of three Once-Through Steam
Generators (OTSG’s) at Devon Energy’s Jackfish 1 thermal in-situ operations and estimate the capital
expenditure for the facilities within +/-15% accuracy.
The process utilizes HTC Purenergy Carbon Capture Technology to capture CO2 from the OTSG exhaust
gas using an aqueous chemical solvent in an absorber tower, after which the CO2-loaded solvent is
passed to a stripper tower where the CO2 is released and the solvent regenerated. The study excludes
downstream CO2 compression, dehydration, transportation and storage.
Rayburn Energy Station / Sherman Power Plant
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Facility scope
EngineeringBechtel
Point source approachPost-Combustion Capture
CO₂ concentration6.0% mol%
Flue gas pressure—
Compressor nameplate—
Compression stages4
Compression inlet—
Compression discharge2,190 psia
Description
Bechtel National Inc., with the Electric Power Research Institute, is conducting a FEED study to retrofit Panda Power Funds’ 758 MWe natural gas combined cycle plant in Sherman, Texas, with a post-combustion CO₂ capture system. Using an open-access design and a conventional amine absorber-stripper system with a non-proprietary solvent such as MEA, the project targets CO₂ capture for enhanced oil recovery.
CEMEX / Balcones Cement Plant
CO₂ captured
744,235t/yr
Capture efficiency
75.0%
Utilization
90.0%
Parasitic load
36MW
CO₂ concentration
14.9%vol%
Facility scope
EngineeringSargent & Lundy
Point source approachPost-Combustion Capture
CO₂ concentration14.9% vol%
Flue gas pressure14 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge2,213 psia
Description
Membrane Technology & Research Inc., with Sargent & Lundy and CEMEX, is designing a full-scale Polaris membrane CO₂ capture system for the CEMEX Balcones cement plant in New Braunfels, Texas, targeting about 1 million tonnes of CO₂ capture annually. The study will develop the design basis, process design, cost estimates, permitting and safety reviews, constructability assessment, and a techno-economic analysis. Sargent & Lundy will lead the design work, while CEMEX will provide site-specific data for integration.