Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Facility scope
EngineeringHTC Puretech
Point source approachPost-Combustion Capture
CO₂ concentration8.6% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge
Description
A Front End Engineering and Design (FEED) study was undertaken to design an advanced CO2 Capture Unit (CCU) to produce 1000 tonnes per day of CO2 from the exhaust of three Once-Through Steam Generators (OTSG’s) at Devon Energy’s Jackfish 1 thermal in-situ operations and estimate the capital expenditure for the facilities within +/-15% accuracy. The process utilizes HTC Purenergy Carbon Capture Technology to capture CO2 from the OTSG exhaust gas using an aqueous chemical solvent in an absorber tower, after which the CO2-loaded solvent is passed to a stripper tower where the CO2 is released and the solvent regenerated. The study excludes downstream CO2 compression, dehydration, transportation and storage.

Peterhead Power Station (Aberdeenshire)

Natural GasFEED· Shell· Project page ↗Cost report ↗
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
Parasitic load
MW
CO₂ concentration
Facility scope
Engineering
Point source approachPost-Combustion Capture
CO₂ concentration
Flue gas pressure
Compressor nameplate
Compression stages
Compression inlet
Compression discharge1,754 psia
Description
The Peterhead CCS Project in Aberdeenshire, Scotland, was designed to demonstrate the world’s first commercial-scale post-combustion CO₂ capture from a gas-fired power station. Using amine-based CANSOLV technology, it aimed to capture around one million tonnes of CO₂ annually from one turbine at SSE’s Peterhead Power Station, compress and condition it, and transport it via a new offshore pipeline for injection into the depleted Goldeneye gas reservoir over 2 km beneath the North Sea. The FEED study defined project scope, refined CAPEX and OPEX estimates, and assessed cost uncertainties, providing a basis for the Execute phase while also documenting budget performance and emergent costs during FEED.

Finnish Integrated Pulp and Board Mill / Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln

Pulp and Paperpre-FEED· VTT Technical Research Centre of Finland· 2016-12-01Project page ↗Cost report ↗
CO₂ captured
1,946,575t/yr
Capture efficiency
90.0%
Utilization
95.9%
Parasitic load
31.4MW
CO₂ concentration
15.7%mol%
Facility scope
Engineering
Point source approachPost-Combustion Capture
CO₂ concentration15.7% mol%
Flue gas pressure
Compressor nameplate
Compression stages4
Compression inlet
Compression discharge1,595 psia
Description
Analysis sets the design and cost-estimating basis for evaluating pulp and board mills with and without CCS. Two base cases are considered: a market pulp mill and an integrated pulp and board mill. Six CCS cases are evaluated, capturing CO₂ from the recovery boiler, multi-fuel boiler, lime kiln, or their combinations. The mills are assumed to be energy independent, with black liquor and bark burned to produce steam and electricity, and excess electricity exported to the grid. The CO₂ capture system uses post-combustion MEA technology with a 90% capture rate, and if on-site electricity is insufficient, an auxiliary boiler firing forest residues will supply the additional energy. Capture of CO2 in Kraft, Multi-fuel Boilers & Lime Kiln