Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Devon Energy / Jackfish-1 Oil Sands
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
—MW
CO₂ concentration
8.6%mol%
Facility scope
EngineeringHTC Puretech
Point source approachPost-Combustion Capture
CO₂ concentration8.6% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
A Front End Engineering and Design (FEED) study was undertaken to design an advanced CO2 Capture
Unit (CCU) to produce 1000 tonnes per day of CO2 from the exhaust of three Once-Through Steam
Generators (OTSG’s) at Devon Energy’s Jackfish 1 thermal in-situ operations and estimate the capital
expenditure for the facilities within +/-15% accuracy.
The process utilizes HTC Purenergy Carbon Capture Technology to capture CO2 from the OTSG exhaust
gas using an aqueous chemical solvent in an absorber tower, after which the CO2-loaded solvent is
passed to a stripper tower where the CO2 is released and the solvent regenerated. The study excludes
downstream CO2 compression, dehydration, transportation and storage.
Peterhead Power Station (Aberdeenshire)
CO₂ captured
1,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
Facility scope
Engineering—
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure—
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge1,754 psia
Description
The Peterhead CCS Project in Aberdeenshire, Scotland, was designed to demonstrate the world’s first commercial-scale post-combustion CO₂ capture from a gas-fired power station. Using amine-based CANSOLV technology, it aimed to capture around one million tonnes of CO₂ annually from one turbine at SSE’s Peterhead Power Station, compress and condition it, and transport it via a new offshore pipeline for injection into the depleted Goldeneye gas reservoir over 2 km beneath the North Sea. The FEED study defined project scope, refined CAPEX and OPEX estimates, and assessed cost uncertainties, providing a basis for the Execute phase while also documenting budget performance and emergent costs during FEED.
Southern Company / Plant Barry
CO₂ captured
2,400,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
CO₂ concentration
99.0%vol%
Facility scope
EngineeringTrimeric
Point source approachCompression and Dehydration
CO₂ concentration99.0% vol%
Flue gas pressure—
Compressor nameplate24.8 MW
Compression stages6
Compression inlet30 psia
Compression discharge2,065 psia
Description
This report summarizes Trimeric’s Phase II work under the SSEB ECO2S project in Kemper County, Mississippi, focused on Task 7 – Infrastructure Development. Trimeric evaluated CO₂ compression and dehydration costs, compared pumping versus compression for dense phase CO₂, and developed pipeline transport cost estimates. Using experience from past projects, screening-level designs and cost estimates were prepared for a nominal 1 MTPY case and scaled to site-specific conditions. Results showed that increasing discharge pressure modestly raises costs, with pumping offering slight savings and operational flexibility but added complexity. Pipeline costs were estimated using NPC benchmarks, while compression and dehydration costs were scaled for Plant Daniel, Plant Miller, and Kemper. Overall, capital costs were roughly three times equipment costs, with electricity for compression as the dominant operating expense. The costs are associated with Six-stage compression to 1,500 psig, followed by pumping to 2,050 psig