Tools

Carbon Capture Costs: FEED & pre-FEED Cost Reports

Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

CEMEX / Balcones Cement Plant

Cementpre-FEED· Sargent and Lundy· 2026-01-01Cost report ↗
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
MW
CO₂ concentration
12.8%mol%
Facility scope
EngineeringSargent and Lundy
Point source approachPost-Combustion Capture
CO₂ concentration12.8% mol%
Flue gas pressure14 psia
Compressor nameplate46 MW
Compression stages5
Compression inlet
Compression discharge2,215 psia
Description
The CEMEX Balcones Carbon Capture project is a DOE-supported Front-End Engineering Design (FEED) study evaluating commercial-scale deployment of RTI International’s non-aqueous solvent (NAS) technology at the Balcones cement plant in New Braunfels, Texas. The study assessed capture of approximately 2.4 million tonnes of CO₂ per year at roughly 95% capture efficiency from cement kiln flue gas and an associated natural gas–fired boiler, developing an AACE Class 3 cost estimate and detailed engineering design to support future investment decisions. Led by RTI International with KBR as EPC engineering contractor and SLB Capturi as owner’s engineer and technology licensor, the project evaluated integration challenges such as limited cooling water availability, resulting in a hybrid air- and water-cooling configuration. The FEED estimated total project capital costs of about $849 million and annual operating costs of approximately $109 million, providing a techno-economic basis for large-scale cement decarbonization and future project execution planning.

Rayburn Energy Station / Sherman Power Plant

Natural GasFEED· Bechtel· 2022-03-01Project page ↗Cost report ↗
CO₂ captured
645,000t/yr
Capture efficiency
85.0%
Utilization
57.0%
Parasitic load
67.3MW
CO₂ concentration
6.0%mol%
Facility scope
EngineeringBechtel
Point source approachPost-Combustion Capture
CO₂ concentration6.0% mol%
Flue gas pressure
Compressor nameplate
Compression stages4
Compression inlet
Compression discharge2,190 psia
Description
Bechtel National Inc., with the Electric Power Research Institute, is conducting a FEED study to retrofit Panda Power Funds’ 758 MWe natural gas combined cycle plant in Sherman, Texas, with a post-combustion CO₂ capture system. Using an open-access design and a conventional amine absorber-stripper system with a non-proprietary solvent such as MEA, the project targets CO₂ capture for enhanced oil recovery.

Devon Energy / Jackfish-1 Oil Sands

Natural GasFEED· Devon Energy· 2011-11-01Project page ↗Cost report ↗
CO₂ captured
365,000t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
MW
CO₂ concentration
8.6%mol%
Facility scope
EngineeringHTC Puretech
Point source approachPost-Combustion Capture
CO₂ concentration8.6% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge
Description
A Front End Engineering and Design (FEED) study was undertaken to design an advanced CO2 Capture Unit (CCU) to produce 1000 tonnes per day of CO2 from the exhaust of three Once-Through Steam Generators (OTSG’s) at Devon Energy’s Jackfish 1 thermal in-situ operations and estimate the capital expenditure for the facilities within +/-15% accuracy. The process utilizes HTC Purenergy Carbon Capture Technology to capture CO2 from the OTSG exhaust gas using an aqueous chemical solvent in an absorber tower, after which the CO2-loaded solvent is passed to a stripper tower where the CO2 is released and the solvent regenerated. The study excludes downstream CO2 compression, dehydration, transportation and storage.