Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
CEMEX / Balcones Cement Plant
CO₂ captured
2,400,000t/yr
Capture efficiency
95.0%
Utilization
74.0%
Parasitic load
—MW
CO₂ concentration
12.8%mol%
Facility scope
EngineeringSargent and Lundy
Point source approachPost-Combustion Capture
CO₂ concentration12.8% mol%
Flue gas pressure14 psia
Compressor nameplate46 MW
Compression stages5
Compression inlet—
Compression discharge2,215 psia
Description
The CEMEX Balcones Carbon Capture project is a DOE-supported Front-End Engineering Design (FEED) study evaluating commercial-scale deployment of RTI International’s non-aqueous solvent (NAS) technology at the Balcones cement plant in New Braunfels, Texas. The study assessed capture of approximately 2.4 million tonnes of CO₂ per year at roughly 95% capture efficiency from cement kiln flue gas and an associated natural gas–fired boiler, developing an AACE Class 3 cost estimate and detailed engineering design to support future investment decisions. Led by RTI International with KBR as EPC engineering contractor and SLB Capturi as owner’s engineer and technology licensor, the project evaluated integration challenges such as limited cooling water availability, resulting in a hybrid air- and water-cooling configuration. The FEED estimated total project capital costs of about $849 million and annual operating costs of approximately $109 million, providing a techno-economic basis for large-scale cement decarbonization and future project execution planning.
Linde / Port Arthur Facility
CO₂ captured
1,435,000t/yr
Capture efficiency
92.0%
Utilization
90.0%
Parasitic load
—MW
CO₂ concentration
16.2%mol%
Facility scope
EngineeringKiewit (EPC costs for Svante’s equipment, steam generators, and OSBL construction), Linde (EPC costs for CO₂ purification/compression and EP costs for OSBL utilities)
Point source approachPost-Combustion Capture
CO₂ concentration16.2% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
Linde Inc., with Linde Engineering Americas, Linde Engineering Dresden, and Svante Inc., is completing an initial engineering design for a commercial-scale CO₂ capture plant at its steam methane reforming hydrogen facility in Port Arthur, Texas. Using Svante’s VeloxoTherm™ solid adsorbent technology, the system will capture about 1 million tonnes of CO₂ annually at ≥90% efficiency while producing 99.97% pure “blue” hydrogen. The design will include ISBL units for flue gas conditioning and CO₂ purification, OSBL components, and a techno-economic analysis of capture costs and hydrogen production economics.
Nutrien Redwater Nitrogen Operations
CO₂ captured
1,778,645t/yr
Capture efficiency
99.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge2,614 psia
Description
Studied the replacement of the SMR units with auto-thermal reforming (ATR) technology. ATRs produce a high concentration CO₂ stream, instead of low concentration combustion flue gases, that is more efficient to capture for sequestration. H₂ production from the unit may also be oversized to provide H₂ as a fuel source for the ATR if target overall CO₂ recovery of the facility is not achieved with the replacement of the SMR alone. The facility capacity is based on the total H₂ production requirements of the existing Plant 01 and Plant 09 ammonia synthesis units. 3 | P a g e Public – Approved for external distribution The scope for the study involves the SMR unit replacement with an integrated ATR and downstream syngas purification including CO₂ capture. The project scope also includes an Air Separation Unit (ASU) to supply oxygen to the ATR unit.