Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.

3 of 3 selectedClear selection46 reports
Comparing 3 reports — tab selection applies to every column.

Milton R. Young Power Plant

CoalFEED· Minnkota Power Cooperative· 2023-02-20Project page ↗Cost report ↗
CO₂ captured
4,297,145t/yr
Capture efficiency
90.0%
Utilization
85.0%
Parasitic load
83.3MW
CO₂ concentration
8.6%vol%
Facility scope
EngineeringFluor
Point source approachPost-Combustion Capture
CO₂ concentration8.6% vol%
Flue gas pressure
Compressor nameplate44.4 MW
Compression stages
Compression inlet
Compression discharge1,690 psia
Description
Milton R. Young Station Unit 2 is conducting a FEED study to add a post-combustion CO₂ capture system using Fluor’s Econamine FG Plus™ technology to its lignite-fueled power plant in North Dakota. The design targets 3.6 million tonnes of CO₂ captured annually—twice the scale of the largest existing facility—while integrating advanced heat recovery, aerosol and solvent degradation controls, and cold-climate optimization to achieve the lowest levelized cost of capture at world scale. The study will deliver detailed design, cost, and performance data for financing, permitting, and final project scheduling.

Phillips 66 / Rodeo Refinery

Hydrogenpre-FEED· Phillips 66 Company· 2023-08-09Project page ↗Cost report ↗
CO₂ captured
190,000t/yr
Capture efficiency
95.0%
Utilization
94.5%
Parasitic load
MW
CO₂ concentration
18.0%vol%
Facility scope
EngineeringWorley
Point source approachPre-Combustion Capture
CO₂ concentration18.0% vol%
Flue gas pressure20 psia
Compressor nameplate
Compression stages5
Compression inlet25 psia
Compression discharge2,250 psia
Description
Phillips 66, with Worley Group Inc., is developing the initial design for a commercial-scale CCS system at the Rodeo Refinery hydrogen plant, targeting over 90% capture efficiency and storage of about 190,000 tonnes of CO₂ annually. The project will evaluate three capture configurations—flue gas plus PSA tail gas, syngas plus flue gas, and flue gas only—selecting the most cost-effective option through a techno-economic analysis. The chosen design will be advanced to a level suitable for the next engineering phase, concluding with a final TEA for the selected CCS configuration.

Nutrien Redwater Nitrogen Operations

AmmoniaFEED· Nutrien· 2024-11-01Project page ↗
CO₂ captured
683,645t/yr
Capture efficiency
99.0%
Utilization
Parasitic load
MW
CO₂ concentration
7.0%mol%
Facility scope
EngineeringHatch
Point source approachPost-Combustion Capture
CO₂ concentration7.0% mol%
Flue gas pressure15 psia
Compressor nameplate
Compression stages
Compression inlet
Compression discharge2,614 psia
Description
Scope starts with the receipt of natural gas and fuel gas mixture from the existing Plant 01 and Plant 09 source and terminates with hydrogen (H₂) at the required specification and conditions to be used as fuel in the existing SMR unit. High concentration CO₂ from the ATR is captured and H₂ production from the proposed facility will replace the fuel gas feed to the primary reformer for heating. The facility capacity is based on the heating duty required to replace the current fuel source. The scope for the study involves the new ATR unit and associated downstream shift, CO₂ capture, and syngas purification unit. The project scope also includes an ASU to supply oxygen to the ATR unit.