Tools
Carbon Capture Costs: FEED & pre-FEED Cost Reports
Carbon capture costs from pre-FEED and FEED studies across power, cement, steel, natural gas, hydrogen and other industrial sectors. Browse capital (capex) and operating (opex) cost estimates from publicly available engineering reports, drill down into cost buckets and line items, and compare up to three projects side-by-side.
Comparing 3 reports — tab selection applies to every column.
Southern Company / Plant Daniel
CO₂ captured
1,769,520t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
79MW
CO₂ concentration
—
Facility scope
EngineeringLinde Engineering (ISBL), Southern Company Services (OSBL)
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure15 psia
Compressor nameplate—
Compression stages—
Compression inlet—
Compression discharge—
Description
Southern Company Services, with Linde Gas North America, is conducting a FEED study for a commercial-scale CO₂ capture system using Linde-BASF’s advanced aqueous amine technology at an NGCC plant of at least 375 MWe. The project will evaluate Alabama Power’s Plant Barry and Mississippi Power’s Plant Daniel to select the optimal host site, define project requirements, optimize process design, and deliver engineering packages along with a cost and schedule estimate within 15% accuracy. The study will build on prior feasibility work and site-specific testing.
Scottish Power / Longannet Power Station
CO₂ captured
2,000,000t/yr
Capture efficiency
90.0%
Utilization
—
Parasitic load
—MW
CO₂ concentration
—
Facility scope
EngineeringAker Carbon Capture
Point source approachPost-Combustion Capture
CO₂ concentration—
Flue gas pressure—
Compressor nameplate—
Compression stages5
Compression inlet—
Compression discharge473 psia
Description
In March 2010, the Scottish CCS (Carbon Capture & Storage) Consortium began an extensive Front End, Engineering and Design (FEED) study to
assess what exactly would be required from an engineering, commercial and regulatory, perspective in order to progress the CCS demonstration project at Longannet Power station in Scotland (Goldeneye) through to construction. The study has yielded invaluable knowledge in areas such as cost, design, end-to-end CCS chain operation, health and safety, environment, consent and permitting, risk management, and lessons learnt.
Southern Company / Plant Barry
CO₂ captured
2,400,000t/yr
Capture efficiency
—
Utilization
95.0%
Parasitic load
—MW
CO₂ concentration
99.0%vol%
Facility scope
EngineeringTrimeric
Point source approachCompression and Dehydration
CO₂ concentration99.0% vol%
Flue gas pressure—
Compressor nameplate25.7 MW
Compression stages6
Compression inlet30 psia
Compression discharge2,065 psia
Description
This report summarizes Trimeric’s Phase II work under the SSEB ECO2S project in Kemper County, Mississippi, focused on Task 7 – Infrastructure Development. Trimeric evaluated CO₂ compression and dehydration costs, compared pumping versus compression for dense phase CO₂, and developed pipeline transport cost estimates. Using experience from past projects, screening-level designs and cost estimates were prepared for a nominal 1 MTPY case and scaled to site-specific conditions. Results showed that increasing discharge pressure modestly raises costs, with pumping offering slight savings and operational flexibility but added complexity. Pipeline costs were estimated using NPC benchmarks, while compression and dehydration costs were scaled for Plant Daniel, Plant Miller, and Kemper. Overall, capital costs were roughly three times equipment costs, with electricity for compression as the dominant operating expense. The costs are associated with Six-stage compression directly to 2,050 psig