classVIBluebonnet
Company logo

Oxy

Bluebonnet

Bluebonnet Sequestration Hub LLC plans to inject approximately 1.31 million metric tons (1.31 MMT) of carbon dioxide between the six (6) injector wells each year (MMTPA) for 20 years. Bluebonnet Sequestration Hub LLC plans to inject a cumulative total of 157.2 million metric tons (MMT) into the proposed well over the 20-year injection period of the Bluebonnet Sequestration Project. Carbon dioxide will come from nearby industrial power-generating plants, refineries, and chemical production, natural-gas processing, and natural-gas liquefaction facilities along the Gulf Coast, from the Beaumont/Port Arthur area to the east and to the Houston area in the west. The carbon dioxide captured at these nearby industrial emitters will be compressed into a supercritical, nearly pure carbon dioxide fluid which will then be injected deep underground through the injection well. Bluebonnet Sequestration Hub LLC selected the locations of the six proposed injection wells based on its own geological research and used site-specific data to ensure that the carbon dioxide would be safely stored in the proposed injection formations. The three proposed injection zones from top to bottom are the Lower Miocene, Frio, and Hackberry Formations, perforated across multiple injection intervals ranging in depth between approximately 5,200 – 8,800 feet below ground surface. The Lower Miocene injection reservoir is top-sealed and geologically isolated by approximately 800 feet of very low permeability Miocene Composite Confining Zone and Lower Miocene Shale. The Frio (Oligocene) injection reservoir is top-sealed and geologically isolated by approximately 1,000 feet of overlying Anahuac Shale. The Hackberry (Oligocene) injection reservoir is top-sealed and geologically isolated by approximately 200 feet of overlying Frio shale. The shallowest Lower Miocene injection reservoir at the Bluebonnet Sequestration site lies approximately 3,500 feet below (deeper than) the deepest underground source of drinking water (USDW) at that site.

Capacity
157,200,000 t
Injection rate
7,920,000 t/yr
Status
Pending
Wells
10
Map layers
Overview

Full Project Overview

All key information and technical data related to this project

Overview

Company:
Project name:
Bluebonnet
Project categories:
class_vi
City:
Winnie
County:
Chambers
State:
Texas
Country:
United States of America
Region:
United States
Government funding:
$16,480,117
EPA region:
6
Applicant name:
Bluebonnet Sequestration Hub, LLC
Status:
Pending
Well applications:
6
Injection rate (Mt/year):
7,920,000
Injection years:
20
Total storage capacity (Mt):
157,200,000
Leased acres:
70,000
Announcement date:
2023-03-02
News

Related News

Explore recent news and developments connected to this project.

Date
Article title
Source
2024-10-28
1PointFive and Enterprise Agreement Supports Development of Carbon Dioxide Transportation Network for Southeast Texas Sequestration Hub
2024-10-08
1PointFive Secures More DOE Funding for Sequestration Hubs
2023-03-02
1PointFive Announces Plan to Develop a Carbon Capture and Sequestration Hub in Southeast Texas
Data

Wells

Data for injection rates, perforation, and other well-related metrics.

Bluebonnet USDW 8

API
7132676
Well class
Stratigraphic
Permit date
2024-11-15

Bluebonnet CCS 3

Injection rate (Mt / year)
1,320,000
Injection years
20
Well class
Injector

Bluebonnet CCS 1

Injection rate (Mt / year)
1,320,000
Injection years
20
Well class
Injector
Permit date
2026-08-04

Bluebonnet CCS 5

Injection rate (Mt / year)
1,320,000
Injection years
20
Well class
Injector

Bluebonnet CCS 6

Injection rate (Mt / year)
1,320,000
Injection years
20
Well class
Injector

Bluebonnet CCS 7

Injection rate (Mt / year)
1,320,000
Injection years
20
Well class
Injector

Bluebonnet CCS 2

Injection rate (Mt / year)
1,320,000
Injection years
20
Well class
Injector

Bluebonnet USDW 02

API
7132676
Well class
Stratigraphic
Permit date
2024-10-23

Encanto #01

API
7132664
Well class
Stratigraphic
Permit date
2022-11-21

Bluebonnet USDW 01

API
7132672
Well class
Stratigraphic
Permit date
2024-04-17
Data

Geology

Subsurface data for carbon storage.

Frio

Gross thickness (ft)
284
Depth TVD (ft)
7346

Hackberry

Gross thickness (ft)
52
Depth TVD (ft)
8286

Lower Miocene

Gross thickness (ft)
1004
Depth TVD (ft)
5261
Download

Project Documents

Technical, design, and planning materials outlining the project’s scope, development approach, and implementation details.

Download

Permitted Documents

Official approval, consent, and compliance documents issued by authorities, confirming the project is authorised to proceed.

Permitted files
03-22-2024__Bluebonnet_-_Testing__Monitoring_Plan.pdf
03-22-2024_Bluebonnet_-_Area_of_Review__Corrective_Action_Plan.pdf
03-22-2024_Bluebonnet_-_Construction_Plan.pdf
03-22-2024_Bluebonnet_-_Emergency__Remedial_Response_Plan.pdf
03-22-2024_Bluebonnet_-_Operating_Plan.pdf
03-22-2024_Bluebonnet_-_Plugging_Plan.pdf
03-22-2024_Bluebonnet_-_Post-Injection_Site_Care_and_Site_Closure_Plan.pdf
03-22-2024_Bluebonnet_-_Preoperational_Testing_Plan.pdf
03-22-2024_Bluebonnet_-_Project_Narrative.pdf
03-22-2024_Bluebonnet_-_Testing_Plan.pdf
03-26-2025_Bluebonnet_-_Area_of_Review__Corrective_Action_Plan.pdf
03-26-2025_Bluebonnet_-_CCS_1_Well.pdf
03-26-2025_Bluebonnet_-_CCS_2_Well.pdf
03-26-2025_Bluebonnet_-_CCS_3_Well.pdf
03-26-2025_Bluebonnet_-_CCS_5_Well.pdf
03-26-2025_Bluebonnet_-_CCS_6_Well.pdf
03-26-2025_Bluebonnet_-_CCS_7_Well.pdf
03-26-2025_Bluebonnet_-_Construction_Plan.pdf
03-26-2025_Bluebonnet_-_Emergency__Remedial_Response_Plan.pdf
03-26-2025_Bluebonnet_-_Financial_Responsibility.pdf
03-26-2025_Bluebonnet_-_Plugging_Plan.pdf
03-26-2025_Bluebonnet_-_Post-Injection_Site_Care_and_Site_Closure_Plan.pdf
03-26-2025_Bluebonnet_-_Preoperational_Testing_Plan.pdf
03-26-2025_Bluebonnet_-_Project_Narrative.pdf
03-26-2025_Bluebonnet_-_Stimulation_Plan.pdf
03-26-2025_Bluebonnet_-_Testing__Monitoring_Plan.pdf
05-09-2024_Bluebonnet_-_Financial_Responsibility.pdf
05-09-2024_Bluebonnet_-_Project_Narrative.pdf
09-12-2024_Bluebonnet_-_Area_of_Review__Corrective_Action_Plan.pdf
09-12-2024_Bluebonnet_-_Construction_Plan.pdf
09-12-2024_Bluebonnet_-_Emergency__Remedial_Response_Plan.pdf
09-12-2024_Bluebonnet_-_Environmental_Justice.pdf
09-12-2024_Bluebonnet_-_Financial_Responsibility.pdf
09-12-2024_Bluebonnet_-_Plugging_Plan.pdf
09-12-2024_Bluebonnet_-_Post-Injection_Site_Care_and_Site_Closure_Plan.pdf
09-12-2024_Bluebonnet_-_Preoperational_Testing_Plan.pdf
09-12-2024_Bluebonnet_-_Project_Narrative.pdf
09-12-2024_Bluebonnet_-_Stimulation_Plan.pdf
09-12-2024_Bluebonnet_-_Surveillance_Plan.pdf
09-12-2024_Bluebonnet_-_Testing__Monitoring_Plan.pdf